Highways England cancels or delays one in three major road schemes

Tristan Shale-Hester 2019-07-19 14:50

Highways England was meant to start 112 major road schemes between 2015 and 2020, but 39 have been cancelled, paused or delayed

Highways England has cancelled or delayed around 35 per cent of major road schemes originally scheduled to start by 2020 at the latest.

The Government-owned body, which is responsible for maintaining major roads in England, was due to start 112 improvement projects across the country between 2015 and 2020, as part of a £15bn five-year road investment strategy announced in 2014.

£317m traffic reduction scheme makes some journeys longer

The organisation’s 2019/20 delivery plan, however, has revealed that 10 of these have been cancelled, paused or are under review. A further 29 have been delayed until the next five-year investment period, which means that it’s possible work won’t commence until as late as 2025.

One of the major schemes that has been cancelled is the improvement of the A27 Chichester Bypass in West Sussex, which was halted when local councils withdrew their support for Highway’s England’s proposed plans for the project.

Other schemes that have been cancelled, paused or placed under review include improvements to the M53 junctions five to 11 and junction 10a of the A14 in the Midlands.

Motorway red X signs now enforced by cameras

Meanwhile, plans for works on the A27 Arundel Bypass, the M6 junctions 21a-26 and the A38 Derby junctions have, among others, been delayed until the next five-year period, scheduled from April 2020 to March 2025.

A spokesperson for Highways England said: “In total, we are progressing over 90 per cent of schemes proposed in the original road investment programme in 2015. It was always presumed that there would be change to the first road investment programme, particularly with the large number of schemes that were at the very early stages of design.

“As they are designed and progressed, we do further analysis, listen to stakeholders and examine environmental issues in more detail. In a small minority of cases we have concluded that schemes do not represent value for money or are unacceptable to stakeholders.

“In these cases, it is right that the schemes should not go ahead. While improving our roads, we do as much as we can to minimise disruption and the effect of the road network on the environment.”

Do you think more needs to be done to improve Britain's roads? Let us know below…

About Alex Ward

Check Also

New Mercedes A 250 e and B 250 e plug-in hybrids revealed

Luke Wilkinson 2019-08-19 11:20 Mercedes has unveiled a pair of new plug-in hybrid vehicles, with a claimed all-electric range of around 40 miles Mercedes has launched plug-in hybrid variants of the A-Class and B-Class, called the A 250 e and B 250 e respectively. The A 250 e will be priced from £32,500 for the hatchback and £33,100 for the saloon, while the B 250 e MPV will start from £33,700. All three models will be available to order in October, with first deliveries expected in early 2020. Merc’s PHEV powertrain comprises a turbocharged 1.3-litre four-cylinder petrol engine (lifted from the mid-range A 200), a 15.6kWh lithium-ion battery pack, and a 75kW electric motor. The powertrain is mated to an eight-speed dual-clutch automatic transmission, with total system output standing at 215bhp and 450Nm of torque. • Best plug-in hybrids on sale now As a result, the A 250 e hatch has a 0–62mph time of 6.6 seconds, a top speed of 146mph, and a claimed (WLTP-rated) all-electric range..

Leave a Reply

Your email address will not be published. Required fields are marked *